Phase 2 of the road construction at the roundabout to be located at Woodcrest Avenue and West Sixth Street began today, June 24. During the road construction, closures and detours will be in effect.
Phase 2: Starting Wednesday, June 24, 2020 and lasting until Monday, July 6, 2020. During Phase 2, parts of West Sixth Street will be closed which will prevent traffic on West Sixth Street from crossing Woodcrest Avenue and also prevent traffic on Woodcrest Avenue from turning onto West Sixth Street. Woodcrest Avenue will remain open to traffic.
Phase 3: Starting Monday, July 6 and lasting approximately 8-10 weeks. The entire intersection of Woodcrest Avenue & West Sixth Street will be closed to all points. All traffic on both roadways will need to follow the detour route.
- Detour routes have been posted for drivers in the area.
- Please plan ahead and leave sufficient time to accommodate the detours.
- While this project is located in Warwick Township, due to the close proximity to, and the detour routes entering into Lititz Borough, there may be residual impacts to Lititz Borough roadways.
Please reference the attached mapping which corresponds to Phase 2 and 3.